Tuesday 24 June 2008

Schedule updated

Week 2: 23rd - 29th June
Priority:
panels 12-16 flat roof and windowed interior; meteor test; building texture photographs; then pre-viz models for rest of movie.

  • Environmental design [Tasked: Jenny and Dave Ball]
  • Compositing [Tasked: Dave Bentick]
  • Friday 11:30 C431 - Production meeting to discuss and review project.
    Need to sign off panels 12-16 pre-viz, and to set targets for next panels

Week 3: 30th June - 6th July

  • Environmental design [Tasked: Jenny and Dave Ball]
  • Compositing [Tasked: Dave Bentick]
  • Friday 11:30 C431 - Production meeting to discuss and review project.

Week 4: 7th - 13th July

  • Environment rendering and videos captured. [Tasked: Jenny and Dave Ball]
  • Compositing [Tasked: Dave Bentick]
  • Friday 11:30 C431 - Production meeting to discuss and review project.

Week 5: 14th - 20th July

  • Compositing [Tasked: Dave Bentick]
  • Friday 11:30 C431 - Production meeting to discuss and review project.

Week 6: 21st - 27th July

  • Editing [Tasked: Adam Hamilton]
  • Friday 11:30 C431 - Production meeting to view edited video.

Week 7: 28th July -

  • Post-production and credits [Tasked: Dave Bentick & Matt Frodsham]
  • Friday 11:30 C431 - Production meeting to view final version of video. Discuss and decide soundtrack ideas. Lock video off for scoring/sound.

No comments:

Post a Comment